|
||||||
Project Planning and Estimating for ManagersGuide Project Manager to Good Project Estimation for Project Success
Project planning requires good project estimating to produce an achievable project schedule and a greater chance of on-time delivery. Managers should guide the process.
Software project management offers some guidance but no hard and fast rules, so consequently project managers have a great deal of discretion in determining what project estimating approach is taken. Those project estimates become central to producing the project schedule, which is hopefully not a work of fiction although inevitably many are exactly that. Managers need to understand project estimation and ensure project managers produce good project estimates and so increasing the chances of a successful project. Approach to Project EstimationProject estimating is very important and a number of different approaches have developed such as PERT [Program Evaluation and Review Technique], COCOMO [Constructive Cost Model] or Delphi Method. Whilst each technique has its strengths and weaknesses it is not always clear that any project estimating technique is sufficiently reliable to produce accurate estimates and schedules. This is primarily because:
Project Planning is too OptimisticProject planning is based on the project scope and objectives, which should be clearly defined during project initiation, and project estimates of the tasks involved. Most projects take longer than expected primarily due to over-optimism from both the project manager and the experts producing estimates. Project managers should be encouraged to use PERT for the critical tasks of the projects if not all tasks to compensate for over optimistic estimates. All project managers will have been taught PERT using this formula:
It is simple to understand – each task is given three estimates of time to complete that task:
Then the formula is used to take the average to produce a project estimate of time to complete that task – 4.5 days [(2+ 4x4 +9) / 6] Project Estimating for ManagersSome project managers do not use any formal approach to obtaining project estimates for the project planning phase. Instead, they typically rely on task estimates from the “experts”. Unfortunately, this tends to produce the most optimistic delivery date. Managers may believe that this date is achievable or it seems a long way off and so must be easily achievable, however, often that is not the case. As a manager how do you influence the project manager to produce a better, more realistic, schedule? Better Project Estimates for Better Project SchedulingThe key to better estimates is to look for the likely causes of estimates to be wrong and to get the project manager to compensate for them:
Producing better project estimates up-front is more likely to lead to more realistic project scheduling and consequently a successful project.
The copyright of the article Project Planning and Estimating for Managers in Business Project Management is owned by Roger Lever. Permission to republish Project Planning and Estimating for Managers in print or online must be granted by the author in writing.
|
||||||
|
|
||||||
|
|
||||||